Middleburg Heights’ Indian Creek sewer project has two published completion expectations and several different financial measures. The City’s project page points to October 2027, while its linked presentation shows September 2027. Neither is a completion certificate.

What is dated, and what is only scheduled?

LSL aligned the signed Phase 1 resolution, project update and linked public presentation:

Date or periodWhat the record actually says
February 27, 2026Bid received, according to the resolution
April 14–17, 2026Council passed the resolution April 14; mayor approved it April 15; publication/posting is marked April 17
July 13, 2026City project page reports construction began
July 2026–September 2027Construction window shown in the linked presentation
Through October 2027Expected duration stated on the project page reviewed September 20

The April 17 date in the original resolution webpage’s URL is therefore not the Council adoption date. The presentation filename identifies June 29, 2026; we have not independently confirmed when it was delivered.

The differing September/October endpoints deserve a question to the City, not an invented explanation for a delay. This comparison does not establish the percentage complete today.

Do not add the appropriation to the contract amount

These figures answer different questions:

AmountSource and meaning
$10,284,080Only bid identified and contract authorized by Resolution 2026-28 for Phase 1
$1,854,300Additional appropriation in that resolution; not a second construction award
$10,719,080Total project budget shown in the public presentation
$7,143,000 outside funding + $3,576,080 City sharePresentation’s funding components, which add to its budget

LSL reproduced the funding sum: $7,143,000 + $3,576,080 = $10,719,080. The presentation budget exceeds the authorized bid by $435,000. The reviewed records do not allocate that difference, so it should not be labeled contingency, an overrun or extra contractor payment.

The presentation also identifies a $2 million grant application. An application is not an award; do not subtract it from the City’s stated share as though funding had arrived. Authorization and a planning budget likewise do not establish final expenditure.

Check the work affecting your frontage

The City describes trenching, boring, sewer installation and restoration of pavement, concrete aprons and trees. It plans one-way eastbound traffic on Indian Creek between Baldwin Creek and Gerald during portions of construction—not necessarily on every day within the project window.

Before arranging deliveries or driveway access, check the current project page and ask the City’s project contact about the specific address and date. A useful request identifies the frontage, planned access need and whether the question concerns excavation, temporary access or final restoration. The general timetable cannot answer those separately.

Reporting scope

This September 20, 2026 review read the operative project update, both pages of the signed resolution and text from all nine presentation pages. The project page displays an August 29 update; viewing it today does not turn every July forecast into a newly verified milestone.

LSL created the date comparison and reproduced the arithmetic. We did not inspect construction, verify a current traffic arrangement, review a signed construction contract or final payment, or map impacts to individual addresses.