DOTD’s September 2, 2026 update says construction continues on the North 18th Street and Forsythe Avenue project. The City’s copy stops at June 1; it is missing three later updates that remain visible in the state record. Neither page supplies a final completion date. DOTD rolling notice City copy
Eleven entries in the state record
The DOTD record contains the October 31, 2025 original and ten continuation updates. The City copy reproduces the first eight entries:
| Record date | What the record establishes |
|---|---|
| October 31, 2025 | Work was scheduled to begin November 10, weather permitting, on LA 840-6 from Hudson Lane to Bayou Desiard |
| November 3, 2025 | Text says construction continued before the originally scheduled November 10 start |
| January 6, 2026 | Construction continued |
| February 3, 2026 | Construction continued |
| March 4, 2026 | Construction continued |
| April 1, 2026 | Continued work; pipe repair beginning April 6 was expected to require a closure under 14 days |
| May 4, 2026 | Construction continued |
| June 1, 2026 | Construction continued |
| July 7, 2026 | Construction continued; this update is absent from the reviewed City copy |
| August 3, 2026 | Construction continued; this update is absent from the reviewed City copy |
| September 2, 2026 | DOTD’s latest displayed update still reports construction continuing |
From the scheduled November 10, 2025 start to September 2, 2026 is 296 elapsed calendar days. That figure is not days worked. Weather, sequencing, closures, weekends, suspensions, and other conditions are not resolved by subtracting dates.
Do not turn a forecast into a finish
The November 3 continuation wording predates the scheduled November 10 start. Neither statement establishes the actual first workday; the calculation therefore uses the announced date, not an observed start.
The original late-spring target records an expectation at that time. A later “construction continues” entry supersedes any assumption that the road was finished merely because the forecast window arrived. Final completion requires a later authority record.
The April pipe-repair note is also narrow: it identifies a particular activity and expected closure duration. It does not establish that the overall corridor project ended when that activity ended.
Six fields remain open in this record
The reviewed state notice does not establish:
- actual substantial or final completion date;
- final acceptance;
- final contract amount and changes;
- total days worked;
- measured transportation or drainage outcomes; or
- the final disposition of every lane restriction.
For a trip today, use Louisiana 511 and its closure/construction information, or dial 511. Opening the map is not verification that this particular corridor is open. The official Monroe District directory lists 318-342-0100 for the district; the former district-page link no longer reaches that information. A historical article should not be used as a live closure map.
Source and methodology
Local Service Ledger compared the complete City and DOTD notices and checked the 511 interface and official district directory on September 13, 2026. We retained the historical timeline, added the three state-only updates and recalculated the interval between the announced start and latest displayed update. This access date does not turn the September 2 statement into a September 13 field observation. We did not visit the corridor, assess progress, calculate working days, or predict completion.