JXN Water’s project page has two different counts. Its introduction describes 24 projects, while Local Service Ledger counted 27 separate expandable entries on September 13, 2026. The difference is unresolved; neither number should be treated as a count of active construction sites.

This index groups every listed entry by the utility’s own status and adds a short explanation of the work. It also preserves the utility’s type labels—even where wastewater work is labeled drinking water. Source project page

What was counted—and what was not

The introduction’s arithmetic is 13 drinking-water projects + 11 sewer projects = 24. The actual card count is 8 In Progress + 7 Coming Soon + 12 Completed = 27. These are different populations: a headline portfolio description and the page’s displayed entries. The source does not reconcile them.

LSL counted each expandable project heading once, checked for duplicate names, and independently compared the result with the number of project-card elements. Both methods returned 27. The ten process bullets inside the treatment-redundancy entry count as part of that one card, not ten additional projects. This is a dated page inventory, not an audit of contracts or work delivered.

Find an item in the public list

The scope summaries are LSL’s reading of each card. Names, status groups and type labels come from JXN Water. All seven Coming Soon entries retain a drinking-water label although their descriptions concern sewers or wastewater treatment. The resulting label count—23 drinking water and 4 sewer—must not be substituted for the introduction’s 13/11 portfolio split. Names, labels and scope descriptions

In Progress: 8 entries

Utility project nameLSL scope summaryUtility type label
Chemical systems at plants and wellsAutomated chemical dosingDrinking water
Corrosion controlImplementation of the approved corrosion-control planDrinking water
Chlorine system improvements at O.B. CurtisChlorination equipment and operationDrinking water
Distribution system study, analysis, and implementationDistribution modeling and asset planningDrinking water
Resilient power planBackup or redundant electrical supplyDrinking water
Restore full performance and designed redundancy to all treatment processes at OB Curtis and JH Fewell.Treatment-process and pump performance; ten subordinate process itemsDrinking water
SCADA system improvementsSensors, software and operating informationDrinking water
System stabilization and sustainability planLong-term system and financial planningDrinking water

Coming Soon: 7 entries

Utility project nameLSL scope summaryUtility type label
Mill Street Sewer Rehabilitation ProjectSewer reroute around a railroad yard; see the Mill Street section belowDrinking water
Savanna Peak Cell Lagoon CellsCleaning three wastewater lagoon cellsDrinking water
Savanna WWTP 100 MGD Peak Flow Wastewater PumpReplacement of a peak-flow wastewater pumpDrinking water
Savanna WWTP Phase 1B Type 2 ImprovementsMultiple wastewater-plant receiving, treatment and sludge-handling improvementsDrinking water
Savanna WWTP Emergency Repairs/Replace Dewatering EquipmentWastewater piping, sludge-return pump and dewatering equipmentDrinking water
Trahon WWTP RehabilitationWastewater-plant evaluation, corrective program and immediate repairsDrinking water
West Bank Interceptor RehabilitationInterceptor rehabilitation and investigation of river-water inflowDrinking water

Completed: 12 entries

Utility project nameLSL scope summaryUtility type label
Alternative water source planEmergency water-supply planningDrinking water
Annual Sewer Cleaning & CCTV ContractRecurring sewer cleaning and camera-inspection contractSewer
Emergency Small Diameter Pipe ReplacementWater-main replacement and street restorationDrinking water
Emergency Lead Service Line InventoryService-line inventory for identification and replacement planningDrinking water
Emergency Reimbursement for Eligible InfrastructureReimbursement for previously purchased water meters and boxesDrinking water
Emergency Sewer FailuresSewer investigation supporting repair or replacementSewer
Intake Structure RepairsRaw-water intake repairsDrinking water
Investigate Service Request LocationsRecurring investigation of sewer service requestsSewer
O&M ContractWater-system operations and maintenance contractDrinking water
Queens Area Sewer Rehabilitation ProjectSewer rehabilitation in Queens project areasSewer
Sludge assessment in all finished water storage facilitiesStorage sediment assessment and removal planningDrinking water
Winterization of systemDrinking-water facility freeze protectionDrinking water

Mill Street: a sewer reroute, not a dated construction notice

The Mill Street card describes 2,200 linear feet of sewer to be rerouted around a railroad yard after a collapse beneath the tracks. It says the old line would be filled with flowable fill and abandoned in place. LSL’s scale conversion is 2,200 ÷ 5,280 = approximately 0.417 mile; the source’s feet measure remains the controlling scope description. Mill Street card

The card remained under Coming Soon on September 13. It supplies no contractor, award amount, work-start date or traffic/railroad closure schedule. A nearby resident should seek a project-specific access or construction notice before planning around a closure; the category alone supplies none. This is a limitation of the reviewed card, not a claim that those records exist nowhere.

Do not confuse this length with the 2,200 service-request locations described in a separate Completed entry. Feet of pipe and locations awaiting or receiving investigation are not interchangeable measures.

Why the Completed group cannot produce a completion percentage

Its entries include an inventory, reimbursement and recurring service arrangements as well as physical improvements. For example, the sewer-cleaning card describes an annual 100-mile goal; its placement does not independently prove that many miles were cleaned in a particular year. The lead-service inventory is a record-building project, not a statement that every service line has been replaced.

Dividing 12 Completed entries by 27 cards would measure the share of cards in a website section—not physical completion of Jackson’s water and sewer work. We do not publish it as a progress score. Readers seeking current lead-related assistance can use the separate JXN filter-access guide; no project label establishes a household’s water condition.

Move from a card to a dated update

JXN Water’s Resources index separates drinking-water and sewer quarterly reports. At this review, each section’s latest listed quarter was October–December 2025. That is the latest link observed there, not proof that no later report exists. Check the period printed on the report and match the exact project name before treating it as an update.

EPA’s Jackson drinking-water page offers a separate route to orders, reports and EPA comments. Some narrative there refers to earlier periods, including a 2025 litigation-stay date; an access date does not make every statement current. Neither that index nor this one supplies a current compliance determination or construction schedule.

The observation date belongs to LSL’s source check. It is not a project-status effective date supplied by JXN Water. The underlying row inventory retains source status and type separately from our scope summaries so a future review can identify which individual entries changed. No site visit, private account lookup, water testing or independent project-delivery audit was performed.