Finishing earthwork and handing over a development’s drainage facilities are different milestones in Vicksburg. The City’s code separates the site-grading permit, erosion-control responsibilities and long-term stormwater maintenance. A grading approval alone does not transfer a detention pond to the City or release a developer from maintenance.

Establish the applicable permit before calculating its fee

Chapter 6, §§6-273–6-274 requires a grading permit for covered land disturbance but lists exemptions. Single-family construction and additions are exempt from that permit while remaining subject to erosion-control requirements. Home gardens, landscaping and lawn preparation on existing lots are exempt unless erosion or drainage alteration makes a permit necessary. Other exemptions have their own conditions; this is not blanket clearance to change a site’s drainage.

Ask Building & Inspection at 601-634-4528 about the actual area, slopes, downstream drainage and scope. The grading application requests acreage, earthwork cost, site-plan/preliminary-plat approval status, parcel/access information, flood mapping and the engineer’s information. The City, not a completed checkbox, decides applicability and approval.

The general grading webpage uses ambiguous “$50 minimum and $25 per acre” wording. Code §6-273(c) specifies the greater of $50 or $25 for each acre disturbed. It also permits adjustment by City resolution. LSL has not checked for a later fee resolution, and the code does not specify fractional-acre rounding here; obtain the actual charge for the application rather than adding $50 to the acreage amount.

Three handoffs to keep separate

This LSL handoff map is based on the cited code, not a substitute for an engineer’s plan:

MilestoneEvidence or responsibility that mattersWhat does not follow automatically
Grading work proceeds under the approved planUnder §6-285, the holder supplies a phasing schedule, reports changes and checks erosion controls; the City can require corrections and plan amendments.Staying on schedule does not prove that downstream erosion is controlled.
Approved land-stabilization work is completed and finally inspectedWhere §6-283 security applies, release/termination of that security is tied to completion and final inspection. A separate one-year maintenance bond remains.A contractor’s last invoice is not release of the security or maintenance obligation.
An applicable development transfers drainage maintenanceSection 6-291 requires the 80% building/occupancy milestone and final approval, final inspection and a compliance letter before transfer.Reaching 80% alone does not complete the handoff, and transfer does not necessarily mean City ownership.

Section 6-283 applies its security requirement to disturbances above one acre and smaller areas with specified hazardous soil/drainage conditions. It provides for release within 30 days of completion and final City inspection, with a maintenance bond of 10%–50% of the original security for one year, as determined by the director. Those are conditional code provisions, not an estimate of a private project’s bond or a promised refund date.

Who maintains the drainage after transfer?

For developments covered by the stormwater article, §6-291 assigns continuing maintenance to the owner or property owners’ association and calls for maintenance obligations in deeds and plats. It allows an association waiver for subdivisions of five single-family lots or fewer only if the other requirements are met; that is not a waiver of maintenance.

The City’s maintenance provision concerns structures in dedicated public rights-of-way that are necessary to drain municipal streets. Section 6-292 separately allows dedication by Board resolution for qualifying facilities. Before assuming the City maintains a pond, obtain the actual ownership, maintenance and dedication documents.

Check scope at the outset: §6-288 covers residential/nonresidential development exceeding one acre within City jurisdiction and also addresses outside areas receiving City utilities. Ask the authorities how this applies to the actual site rather than treating a County address as automatic exemption. Smaller projects can still have separate grading or erosion-control duties.

LSL checked these provisions in the public code reader on September 13, 2026. The posted standalone stormwater PDF has an unfilled ordinance number and adoption date; the codified provisions identify Ordinance 2006-24, December 4, 2006. No drainage design, private dedication, bond release or later City resolution was verified.

Publication note: This corrected guide replaces the former landscaping article at its old URL; original publication and approval dates are retained.