Pouring concrete or closing a wall can make unfinished inspection work inaccessible. Cleveland’s inspection instructions identify those construction stages in advance; they are not a request to photograph the finished job and seek approval afterward.

Use the schedule below when coordinating a permitted renovation in the City of Cleveland. It combines the City’s inspection stages with a separate column of LSL scheduling questions. The questions are preparation aids, not additional City requirements.

Put the inspection before the irreversible work

Planned operationCity’s inspection pointQuestion to resolve before scheduling the next crew
Place concrete for foundation footers, a slab or garage foundationsBefore concrete placementWhich placement areas are ready, and which permit inspection covers them?
Backfill waterproofing or drain tileBefore backfillingWhat must remain visible for the inspector?
Conceal insulation, plumbing, mechanical or electrical workBefore covering the workAre any separate trade inspections still outstanding?
Cover rough framingBefore framing is concealedDoes the inspector need access to more than the room being finished?
Finish the projectFinal inspection and any required occupancy approvalWhich final results remain outstanding for this permit?

These stages come from the City’s inspection instructions. That page also requires inspection for exterior demolition. It is not an address-specific inspection list: use the actual permits to establish which requests apply to your project.

Make the appointment with the inspector on the permit

The City calls for at least 24 hours’ notice. The inspector’s name and telephone number appear near the upper left of the permit. The instructions say the homeowner must be present and Department-approved drawings must be available at the jobsite. An appointment for work that is not ready can incur a trip fee; the page does not state its amount. Inspection instructions

LSL appointment card—complete one for each requested inspection:

  • Permit number and inspection requested: __________
  • Inspector’s name and direct number from the permit: __________
  • Request made on: __________; appointment confirmed for: __________
  • Homeowner’s attendance arranged: __________
  • Areas ready and accessible: __________
  • Approved drawing sheets available: __________
  • Result and any correction instructions received: __________

A request timestamp is not confirmation of an appointment. Likewise, the appointment itself is not permission to conceal work. Ask the inspector what result or further inspection is needed before proceeding.

Doing the work yourself does not remove the inspection

Cleveland’s homeowner guidance allows owner-occupants of one- or two-family homes to perform work without contractor registration, while keeping permit, plan-review and inspection obligations. Do not extend that statement to a rental property or a different building type.

The actual homeowner affidavit asks the owner to affirm ownership and personal performance of the work. It includes a plan-examiner witness field and must accompany the application. Ask Room 505 about the current signing procedure; do not sign as a do-it-yourself owner merely to supply a permit for someone else’s work.

If the inspector requires corrections

The homeowner guidance says a violation notice sets a period for correcting faulty work. Use the deadline in your actual notice. Do not substitute a generic five-day or thirty-day deadline.

Keep the affected area accessible and clarify the reinspection requirement before booking drywall, backfill or concrete placement. If work is already concealed, tell the inspector what has been covered and ask how to proceed. This guide does not establish that photographs will substitute for access.

How this inspection aid was assembled

LSL combined the inspection instructions, owner-work guidance and actual affidavit on September 13, 2026. The stage questions and appointment card are our organization of those sources; no private jobsite or permit outcome was inspected.