Monroe has published October Plum Street updates for the Georgia Street Pump Station project since its September Beauregard crossing notice. The newest reviewed update schedules continuous work for October 16–23, weather permitting. That period has elapsed; it does not establish that a crossing reopened. Check the exact street and current controls before traveling. This is a notice history, not a live traffic map. October updates City listing

What the October notice changes

The City’s combined notice preserves three stages:

Notice stageAnnounced location or changeLimit of the record
October 6 original releasePlum Street, Georgia to Jackson; planned October 7 start, until further noticeLists Mississippi Street to Winnsboro Road as the primary alternative
October 12 updatePlanned October 13 extension east to 1st Street; eastbound lane closed, westbound retained for local access; Plum/Florida intersection fully closedSays the additional closure lasts until the pipe is pulled; its relative forecast is not a completion report
October 15 updateContinuous work from Jackson to Mississippi beneath Plum, planned October 16–23, weather permittingA work schedule, not confirmation of reopening

These locations supplement the older crossing history below. Do not reuse September’s alternatives as a guaranteed route around October’s work. Ask the City project contact, 318-376-3559, about the particular crossing and follow posted controls. LSL has not inspected the streets or obtained a reopening confirmation. The September 25 reminder remains overdue for that unresolved question.

The earlier September 21 plan and access instructions

The September 17 notice places the crossing on Beauregard Street between the Alabama and Mississippi intersections; it also says the work will cross Alabama and Mississippi streets. Preserve that wording when asking the City about an address rather than drawing a detour map from an ambiguous description.

The notice lists:

  • For residents north of the crossing: Jackson Street, South 2nd Street or Pecan Street.
  • For travel south: Winnsboro Road, Georgia Street or South 4th Street.

Those are the City’s listed alternatives, not independently tested turn-by-turn directions. Follow posted signs and barricades. The notice names Kenneth Rogers, 318-376-3559, for questions. Confirm the exact crossing and current arrangements before relying on an older notice. City announcement.

Five notices, different dates and locations

PostedAnnounced workLocation and timing limit
August 21August 24, 7 a.m.; anticipated reopening at 6 p.m., weather permittingMississippi at Alabama, just south of 203 Mississippi; north-side access via Pecan
August 24August 25, 7 a.m.; anticipated reopening at 6 p.m., weather permittingSame described Mississippi/Alabama crossing; a forecast, not proof of reopening
August 26Heading says August 26; body says August 25, 7 a.m.; until further noticeMississippi at Alabama; the conflicting start dates are unresolved in the notice
September 1September 1, weather permitting; until further noticePecan at Mississippi, crossing just south of 203 Mississippi; north-side access via Alabama
September 17September 21, 7 a.m.; until further noticeBeauregard between Alabama and Mississippi; use the access instructions above

Read the underlying August 21, August 24, August 26, September 1 and September 17 announcements. Publication date, intended start and anticipated reopening are different fields. A repeated project name does not make the notices interchangeable.

The August 26 discrepancy prevents a reliable actual-start date from being inferred from that page alone. Likewise, the two earlier 6 p.m. forecasts do not prove those crossings reopened on time. None of these reviewed announcements provides a confirmed completion record for the entire pump-station project.

What changed in this guide

The earlier article described a “42-foot” force main. The notices use a single-prime notation that we have not independently reconciled with engineering specifications. We removed our unsupported conversion rather than substituting another assumed dimension.

We also replaced the generic project-record checklist with the dated crossing comparison and moved this traffic-access guide out of the household-plumbing category. A roadwork notice does not establish a residential plumbing problem, utility outage or repair recommendation.

Reporting basis

LSL read the five dated City notices on September 19, 2026 and compared their locations, announced schedules and access instructions. A duplicate City page carrying the August 21 text was not counted as a separate event. The September 21 start was prospective during that original review. On September 23 the September 17 notice led the first listing page; the October 4 check found an October 1 fire-chief item ahead of it. Those are historical observations.

On October 28 UTC, LSL read the current first listing page and the complete October Plum Street notice, including all three dated stages. Older notices retain their earlier access dates. We did not inspect streets, telephone the City, verify a construction percentage, obtain an engineering plan or establish reopening. The September 25 reopening-check reminder remains overdue. Confirm current access with the project contact and follow on-site controls.